Taste of Belgium To Open Sixth Location At Phase II of The Banks

With construction expected to wrap up on the second phase of The Banks this coming spring, the development team is celebrating the signing Taste of Belgium as the first retail tenant inside the $67 million project.

After getting his start modestly in 2007 in the back of a produce shop at Findlay Market, Jean-François Flechet has grown Taste of Belgium into a household name regionally. The location on the central riverfront will be Flechet’s sixth, and one of its largest.

“The Banks has been such an important catalyst in the resurgence of downtown Cincinnati,” Flechet told UrbanCincy. “We’re thrilled our locally-owned restaurant will be front and center in the new phase of the development.”

The announcement comes at a time when things are picking up pace at The Banks. Construction work has begun on the new AC Hotel, and infrastructure work has commenced for the third phase of the project.

The Radius

Once complete in spring 2016, phase two will be home to an estimated 2,000 employees at General Electric’s 338,000-square-foot Global Operations Center and 300 new apartments. There will also be approximately 20,000 square feet of street-level retail, of which Taste of Belgium will occupy 4,800 square feet.

Over the years since getting started, Flechet has positioned himself as an outspoken small business advocate, and has been vocal in his support of inner-city development and the improvement of urban mobility through projects like the Cincinnati Streetcar and Red Bike – both of which are located a block from this new location. Due to this passion, Flechet says this location at The Banks just makes total sense.

“Cincinnati has responded so positively to our waffles and one-of-a-kind dining experience and this new venue – right in the heart of the riverfront – will have that same great energy and atmosphere.”

The move also is a nod to the growing preference for local businesses over national chains. In fact, the first phase of The Banks largely relied on national chains to fill out its retail space. But due to changing demographics and consumer trends, Marc Fallon at JR Anderson, who put this deal together, believed that The Banks would be better suited with an establishment like Taste of Belgium.

“Taste of Belgium is a great local success story and Jean-François is a great example of the kind of visionary entrepreneur driving so much of our regional growth,” said Dan McCarthy, project executive for Carter, The Banks’ master developer.

Like its other locations, Flechet says that Taste of Belgium at The Banks will be open seven days a week, serving breakfast, lunch and dinner, along with weekend brunch and unique wine lists and beer selections. There will also be a private dining room, chef’s table and a patio with outdoor dining.

“With all the excitement around our Radius residential community and the new GE office building, we needed a dynamic retail tenant that would appeal to all the new people who will be living and working at The Banks,” McCarthy added. “Taste of Belgium more than fits the bill.”

Categories
Development News

PHOTOS: Center City Construction Updates From October

Downtown Cincinnati and the adjacent areas continue to see both new development and redevelopment of existing structures. In an effort to bring broader awareness to the exciting projects occurring in the city, I snapped pictures throughout October showing the work taking place.

  1. Aqua on the Levee, which includes 239 apartments, an Aloft Hotel, and retail space
  2. Early work on a 15-story, 130 unit apartment building at the intersection of 7th Street and Sycamore Street
  3. Progress on the six-story, 117-room Holiday Inn at 7th Street and Broadway Street
  4. $24 million Alumi Lofts redevelopment of the former school in Pendleton into 142 apartments
  5. Prep work on Phase IIIA of The Banks project
  6. Continued progress on the 10-story General Electric Global Operations Center at The Banks
  7. Redevelopment of a former church into an event space adjacent to Washington Park called The Transept
  8. $27 million redevelopment of the YMCA at Elm Street and Central Parkway
  9. The Radius, bringing 292 apartments to The Banks

While these photos focus on projects in the center city, there are certainly many more exciting projects taking place throughout the city as its boom spreads outward. We’ll get to some of those projects in future updates.

EDITORIAL NOTE: This is the first of what we intend to be a regular monthly feature on UrbanCincy that will take a selected look at construction progress throughout the city. If you have any projects that you would like to have us visit and photograph, please let us know by emailing us at editors@urbancincy.com.

Categories
Business Development News

Project Officials To Move Forward With Phase III of The Banks Ahead of Schedule

Business leaders and public officials from the City of Cincinnati and Hamilton County will gather tomorrow morning to celebrate the groundbreaking of the next phase of work at The Banks.

As has been done in the past at the massive central riverfront development, the first work to be done will be the construction of a public parking garage that will lift the project out of the Ohio River’s flood plain. From there, the existing public streets surrounding the project site will be extended to frame the block.

While the event is being touted as a groundbreaking ceremony, workers from Prus Construction and Beaty Construction began mobilizing on the site to perform preparation work. The news is a bit of a departure from previous announcements that said construction work would hold off until the close of the Bengals season in order to preserve parking for tailgaters at Paul Brown Stadium.

In this particular phase of work, project officials say that 690 parking spaces will be built on two levels that will be connected with the rest of the underground parking deck at The Banks, which has been casually described as one of the largest underground parking structures in North America.

This $29.3 million effort is being jointly funded by the City of Cincinnati, Hamilton County, and the State of Ohio’s Jobs Ohio program. Representatives from the various public agencies funding the project say that it will create an estimated 200 jobs, with at least 30% of the contract totals spent with Small Business Enterprises.

Such a claim for small business inclusion is on-target for what the project has been delivering thus far. As of June 2015, the latest reporting date, The Banks has had an average of 36% small business participation and approximately 17.5% minority and female workforce participation.

Nearby work continues on the private sector vertical construction of Radius, a 291-unit apartment midrise with 19,000 square feet of street-level retail, and the 340,000-square-foot General Electric Global Operations Center.

Once these two phases of work are complete, it will allow for the next phase of Smale Riverfront Park to move forward, and will set the stage for private real estate development south of Freedom Way and in between Race and Vine Streets.

So far, Carter USA and the Dawson Company have yet to reveal what will ultimately be built on top of this latest garage extension, but most suspect it will be some combination of apartments and condominiums.

While The Banks has received much positive praise as of late, it has not come without its struggles. The retail in the first phase of the project continues to find its footing, and the area continues to struggle with a brand identity and architectural designs that people feel are worthy for the prominent piece real estate that this development occupies.

Categories
Development News

$52 Million Residential Tower Appears Poised to Move Forward at Eighth and Sycamore

Following committee approval yesterday, City Council appears poised to approve a $7.3 million financial package that should bring a 130-unit North American Properties project to reality.

Designed by John Senhauser Architects, the $52 million, 15-story residential tower will accelerate the transformation of the northeastern corner of the central business district, where business leaders have been trying to rebrand it as the Eighth Street Design District for its cluster of design agencies.

As City Hall has done in the past, 3CDC will be used to build and operate a 500-space public parking garage, along with 10,000 square feet of commercial space, which is estimated to account for $16.5 million of the total project cost.

The project was first announced two years ago, and will take the place of the former two-story Red Cross building at the southeast corner of Eighth and Sycamore Street.

While the parking garage seems oversized at face value, it is part of a larger development efforts taking place nearby, including a 115-room Holiday Inn that includes no parking at all. As part of that deal, the City of Cincinnati agreed to build a parking garage that would provide 120 spaces. Originally planned to include 610 parking spaces, the new parking garage will support both developments and replaces an aging public garage that once occupied the site.

The relatively quick procession of this project stands in contrast to the 111-unit residential tower North American Properties recently completed called Seven at Broadway. Unlike this yet-to-be-named project, Seven at Broadway took more than a decade to complete, with an above-ground parking garage occupying the site since 2003.

The apartments at Seven at Broadway are some of the priciest in the city, and were pre-leased at a pace that surprised developers and investors. Price points have not yet been identified for this new project.

The completion of the Holiday Inn and this new residential tower will significantly alter this corner of downtown, but many still view the two large surface lots across Sycamore Street as the final major pieces of the puzzle.

The southern of the two lots is controlled by St. Xavier Church, and the northern lot is owned by Columbia Oldsmobile Company.

When General Electric was searching for a site for their new Global Operations Center, which ultimately located at The Banks, a rendering surfaced that showed an office building for GE on the northern of the two lots. Rumors have once again begun circulating online that the mockups might be or could be related to potential corporate offices for General Electric should they take action on their relocation threats to the State of Connecticut.

The full City Council will vote on this financial package on Wednesday

Categories
Development News

Project Officials Ready to Move Forward With Next Phase of The Banks

Officials overseeing the development of The Banks have announced that they will soon proceed with the design and construction of the infrastructure needed for the next phase of the massive riverfront project.

Yesterday, at a special meeting of The Banks Steering Committee, the eight-member group unanimously voted in favor of moving forward with what they expect to be $29.3 million worth of work, which would then provide the platform for millions more in private investment in the form of offices, residences and retail on what is referred to as Lot 24.

As has been the case with all prior phases of the mixed-use development, the City of Cincinnati and Hamilton County will build out the utilities and roadway network, and construct a 690-space, two-level parking garage that will lift the site out of the Ohio River floodplain. Carter and The Dawson Company – the private development team selected for the project – would consider what elements should be included and then proceed with building and leasing out whatever is built on top of the parking decks.

A guiding principle that has not changed since the beginning of the development process is that the underground parking garage will be reserved for public parking, leaving Carter-Dawson to develop additional above-ground parking to satisfy the City’s mandatory parking requirements.

The Steering Committee said that the public work will be funded through the issuance of $22 million in tax increment finance bonds, and $7 million from the State of Ohio. Project officials say issuance of the bonds is expected to come within the coming months.

While the Carter-Dawson team has not yet decided the exact mix for this third phase of work, it is widely expected to be primarily residential. In total, the zoning and infrastructure for the site will allow for around 320,000 to 400,000 square feet of developable space.

The timing of the announcement could not be better, with work rapidly progressing on General Electric’s 338,000-square-foot Global Operations Center, 19,000 square feet of retail space, and the 291 apartments at the phase two site to the immediate north; and with the announcement that AC Hotels will develop the long-sought hotel along Main Street in front of Great American Ball Park.

Phase two work is expected to be completed in phases throughout 2016, while AC Hotel by Marriott is expected to open in spring 2017.

While management with the Cincinnati Bengals expressed some concern over the loss of one of the team’s few remaining tailgating lots, The Banks itself is evolving into more of an entertainment district than many had thought.

In April, state officials approved a new open-container district law that will soon be in place at The Banks; and yesterday, in a separate move, the Cincinnati Reds applied for a zoning variance to allow for the installation of a video board that will overlook Freedom Way – providing live video programming when the surrounding streets are shut down to cars for special events. Such moves could render tailgating lots obsolete as fans move to the streets on game days.

Project officials say the phasing of construction at the 18-acre site has been carefully coordinated between the district’s various stakeholders, along with the construction schedule of Smale Riverfront Park. As park work has moved west so has work at The Banks, and with the latest work on the park taking place just south of phase three of The Banks, the timing makes perfect sense.

If all goes according to plan, this next phase of infrastructure work could begin as soon as January or February – just after the conclusion of the Bengals football season.